PROJECT 04 - Finalization of the Assembly Line Installation Project – Automotive Industry

01/01/2026

Country: USA – South Carolina

Period: 09/2025 – 12/2025

Status: Completed

Sector: Automotive industry

Role: Electrical subcontractor

Team: 3 electricians


Scope of work:

• Technical support for programmers during production line troubleshooting

• ProfiNet diagnostics, measurements and corrective actions

• Cable labeling and identification in the final project phase

• Updates of production line sections (additional cabling, installation of components and

connections)

• Basic construction and modification of cable routes


Project specifics:

The production line was partly active during the project.

Very high emphasis on safety, work organization and quality due to ongoing production and

strict automotive standards.